iCore Automation, takes pride in offering not only industry leading automation but also turn-key solutions for their clients. iCore Automation works with their clients to fully understand the issues surrounding their obstacles in order to provide the most economical and reliable solution. Below are some of the projects that iCore Automation resources have been a part of.
Manufacturing Facility, Longmont, CO
1997 - 2001
- Assisted with Start-up
and ICOs and ACOs.
- Provided design and controls for the Roller Bottle Fill & Withdrawal (RBM)
- Re-designed Incremental Encoder for bottle tracking
- Provided PLC and SCADA support for Cell Culture area and Chromatography Skids
- Provided automation assistance to several groups within the engineering department
SCADA/ControlNet Upgrades, Boulder & Longmont, CO
2002-2003
- Responsible for management, cost control and scheduling of all personnel
- Develop Build procedure for SCADAs and revise R/Ds and SOPs
- Assist with the development of the IQ/OQs
- Tested new SCADA/Clients on test network prior to field start-up
- Firmware upgrades for all PLCs and Remote I/O modules
Manufacturing Expansion Project, Boulder, CO
2001
- Assisted with Start-up
- Provided automation assistance with the Utility systems; WFI, CSG and Chillers
- Performed Ethernet side card firmware upgrades
- Assisted with Validation of several systems within the manufacturing facility
Cell Culture Expansion Project, Boulder, CO
2004-2005
- Provided technical support of all Process Automation (Controllogix, PLC5 & SLCs / iFIX SCADA) for Bioreactors, Media Prep and Media Hold, CIP System, Utility System and Electrical Systems.
- Acting Liaison between Amgen and System Integrators
- Assisted Validation with technical issues concerning the IQ/OQs
- Performed SDT and provided design support
- Managed and assisted Vendor personnel with several SKID installations and start-up
SCADA Upgrade Project, Longmont, CO
2007
- Development of IOQs
- Development of Function Tests
- Provide technical support resolution of Network communication issue
Control System Upgrade, Hayward, CA
2007-2008
- Scope of work included management, scheduling, document generation, system design and system start-up for the Process Utility Controls System (PUCS)
- Automation support of Controllogix PLC, SLC 500, Siemens S7, PanelView, iFIX SCADA, Development of SOPs and SDD
- Design and Implement SCADA/CLIENT Network Architecture on MS 2003 Server
- Provide technical support of the following:
WFI System
, Pure Steam Generator System, CIP System, RODI System
, CDA System
, and Waste Neutralization (Siemens)
- Implement HAMO (Steris) Parts Washer via OPC Server/Client communication
Wastewater Project, Boulder, CO
2008-2009
- Scope of work included management, scheduling, Project Status Reporting
- Supervision of Engineers to meet deliverables
- Technical Lead on all SCADA, PLC and Historian design and implementation
- Attend weekly project meetings to discuss schedule and project road blocks
- Scope of work included the integration of the following systems: Waste Neutralization System, Acid Day Tank
, Caustic Day Tank, Lift Stations
, Sump Pumps
, Surge Tank
and Frac Tank
OSI Pi and RtReports Support, Thousand Oaks, CA
2009
- Develop RtReports for TOFX Project
- Support Control Systems (DCS, PLC, HMI, HIST)
- Install Pi Tag Additions for TOFX Project
- Support BAS Inter-processor Communication
- Provide Support for OSI Pi and DeltaV Communication
with DeviceNet
Robot and PLC/DCS support, Durham, NC
2009
- Support Staubli Robots
- Develop AOQs for Robot Automation Qualifications
- CRF/ACC generation/implementation for Robot System changes
- RS and DDS review
- SLC500 and PanelView 1000 trouble-shooting
- DeltaV/Batch Operation and trouble-shooting
- Assist in the commissioning and qualification of the 12 robot systems
- Assist in execution of Incubator OQ testing
Tech Transfer Project - Robot and Process Automation support, CA
2009
- Support ABB Robotic Storage and Handling System (ABB & RS5000)
- Support Production runs
- Work Order Implementation using Maximo
- Change control for Automation Systems
- Develop PI Notification Strategy for B7
- Lead PI Tag configuration and implementation
- Support Bioreactors (PLC5), UFDF (SLC5/04), and RBM (Mitsubishi PLC & HMI)
Manufacturing Facility – DeltaV, Robot and Process Automation support, CA
2009
- Support Upgrade for Emerson DeltaV DCS for Bioreactors and UFDF
- Support Production runs and ONCALL support
- Work Order creation and implementation
- Data Integrity Solutions and Consulting
- Create Templates for PI Notifications
- Create Validation Process for PI tag qualification
- Create PI tag Standards for Building 7